Construction Update - 9/18/2020

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (9/14/20 to 9/19/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Concrete Slab Pour 2 Stone Fill

  • Concrete Slab Pour 4 Electrical Rough In

  • Concrete Slab Pour 4 Reinforcing

  • Concrete Slab Pour 4 Plumbing

  • Concrete Slab Pour 4 Waterproofing

  • Concrete pour at section of North foundation wall

Level 1:

  • Reinforcing for Elevated Concrete Deck Pour 4

Next week's (9/21/20 to 9/26/20) scheduled work activities:


G2:

  • Stripping of G1 Elevated Formwork

  • Re-shore Installation of G1 Elevated

  • Backfilling of G2 Continuous Foundation Walls Continue

G1:

  • Backfill of Slab on Grade Pour 4 East Complete

  • Backfill of Slab on Grade Pour 2 Starts

  • Installation rebar for West foundation wall next to HSRB – I continues.

  • Installation of Level G1 to 1 Columns over G1 Elevated Slab Deck

  • Waterproofing Slab on Grade Pour 4 East Starts

  • G1 Underground MEP Installation Continues

Level 1

  • Reinforcing for Level 1 Pour 2 Continues

  • Forming Level 1 Pour 4 Starts