This past week's (8/17/20 to 8/22/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Pour G1A Elevated Slab
Forming G1B Elevated Slab complete
Reinforcing Steel install for G1B Elevated Slab starts
MEP insert and sleeve install for G1B Elevated Slab starts
GAB backfill for G1 Slab on Grade Pour 3 continues
G1 MEP underground rough-in continues
Forming and pouring of G1 continuous foundations and foundation walls continues
Level 1
Forming Level 1 Pour 1 Elevated Slab continues
MEP insert and sleeve install for Level 1 Pour 1 Slab starts
Reinforcing steel install for Level 1 Pour 1 Elevated Slab starts
Forming Level 1 Pour 2 Elevated Slab starts
Sitework
Install sanitary sine along Haygood continues
HDPE stormwater piping install along Haygood continues
Next week's (8/24/20 to 8/29/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above. Image 2020.07.30-6 above illustrates this condition.
G1:
Pour G1B Elevated Slab
Subgrade preparation for G1 Slab on Grade Pour 3 starts
G1 MEP underground rough-in continues
Forming and pouring of G1 continuous foundations and foundation walls continues
Level 1
Pour Level 1 Pour 1 Elevated Slab
Forming Level 1 Pour 2 Elevated Slab continues
MEP insert and sleeve install for Level 1 Pour 2 Elevated Slab starts
Sitework
Install sanitary sine along Haygood continues
HDPE stormwater piping install along Haygood continues