Construction Update - 7/31/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (7/27/20 to 8/1/20) scheduled work activities:


G2:

  • Pour G2 Pour B slab on grade

  • Form and pour remaining foundation walls

G1:

  • Forming of G1 Elevated Slab A continues

  • Footing poured at HSRB I/II interface

  • Continuous foundation install in G1 north continues

  • Columns poured in G1 south

  • Slab on grade preparation for G1 slab on grade pour 1

  • Electrical ductbank install continues

  • MEP underground install continues

Next week's (8/3/20 to 8/8/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Forming of G1 Elevated Slab A complete

  • Reinforcing steel install for G1 Elevated Slab A starts

  • Forming of G1 Elevated Slab B starts

  • Forming of foundation wall at HSRB I/II interface

  • Continuous foundation install in G1 north continues

  • Electrical ductbank install continues

  • MEP underground install continues

  • Pour G1 Pour 1 slab on grade