Construction Update - 7/23/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (7/20/20 to 7/24/20) scheduled work activities:


G2:

  • Slab on grade Pour B reinforcing begins

  • Slab on grade Pour B MEP slab inserts install begins

  • Reinforcing install for remaining G2 foundation walls

G1:

  • Elevated slab Pour A forming begins

  • Utilidor reinforcing installed

  • Columns poured for Level 1 in southeast corner of G1

  • MEP underground install continues

  • Lean mix poured under north continuous foundations

  • Slab on grade Pour 1 subgrade preparation begins

Next week's (7/27/20 to 8/1/20) scheduled work activities:


G2:

  • Slab on grade Pour B reinforcing complete

  • Slab on grade Pour B pour

  • Forming and pouring of remaining foundation walls

G1:

  • Form and pour utilidor walls

  • Pour 1 slab on grade top mat rebar

  • Columns poured for Level 1 in southeast corner of G1 continues

  • Slab on grade Pour 1 reinforcing begins