Construction Update- 7/17/2020

  • Writer: emoryhsrb2
    emoryhsrb2
  • Jul 20, 2020
  • 1 min read

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the management team feels that everyone on the job site can continue to work safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (7/13/20 to 7/18/20) scheduled work activities:


G2:

  • Complete remaining continuous footings

  • Backfill of foundation walls continues

  • Form Cyclotron lid

  • Subgrade preparation for slab on grade concrete pour in Area B

G1:

  • Install reinforcing and pour Utilidor footings

  • G2-G1 foundation wall south transition forming and rebar install

  • MEP UG installation continues

Next week's (7/20/20 to 7/24/20) scheduled work activities:


G2:

  • Form remainder of G2 Foundation Walls

  • Install slab reinforcing for Pour B

  • Backfill of foundation walls continues

G1:

  • Install reinforcing and pour Utilidor columns and walls

  • G2-G1 foundation wall south transition forming and rebar install

  • MEP UG installation continues

  • North continuous foundations forming and waterproofing install