This past week's (6/22/20 to 6/27/20) scheduled work activities:
G2:
Continuous footings & foundation walls continue
Installation of rebar and pouring of columns continue
Termite control, vapor barrier, rebar install, and forming of SOG
Continue pouring slab on grade
Plumbing inspections, setting drams in SOG, and Cyclotron piping
G1:
Continuous footings & foundation walls continue
Waterproofing foundations continue
Electrical and plumbing UG installation continues
South G2 to G1 Foundation Wall Transition Continues
Next week's (6/29/20 to 7/03/20) scheduled work activities:
G2:
Foundation wall pours continue
Installation of rebar and pouring of columns continue
Termite control, vapor barrier, rebar install, and forming of SOG
G1:
Spread footings continue
Continuous footings & foundation walls continue
Waterproofing foundations continue
Electrical install of layout boxes and inserts & slab rough-in
Plumbing underground piping, BSL3 piping, and setting sleeves