
This past week's (6/20/22 to 6/25/22) scheduled work activities:
G2
Going 100% clean booties required in this area.
Final Paint
Site Acceptance Testing (SAT) Biorepository
Terrazzo floors have been completed.
G1
Ceiling Grid installation in 3 T MRI Suite.
Door Installation continues. Lighting fixtures in mechanical rooms.
7 T MRI calibration has begun.
Terrazzo Floor installation continues.
View from Level 2 of Atrium from center bridge looking East
Level 1
Operable Smoke evacuation panel installation continues.
Café' Rough in continues.
Level 2
Hanging drywall in East connector/HSRB- I
Installation of Atrium liquid light on level 2 continues.
9 wood ceiling installation continues.
punch walk completed on L2 North tower/Offices
Level 3
Electrical trim out continues.
Symphony bench Installation continues in wet labs.
Level 4
Plumbing Fixture Installation.
Fire Alarm & Electrical device trim out continues various locations.
Level 5
Lighting fixture installation continues
Level 6
ACT Ceiling installation continues
Glass handrail installation continues.
Atrium soffit hanging and ceiling drywall installation continues.
Work continues on balcony ceilings and marble.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Building plenums & installing louvers.
Skin:
Installation of granite continues on the South elevation of building continues.
Installation of Rosa Borba & Marble at SW Entry is underway again.
Marble at balconies on North elevation continues.
HSRB – I Vivarium Expansion:
Installation of ceiling tiles.
Installation of utility connections to HSRB – I completed.
Work continues in GNOTO room.
Site:
Installation concrete pathways on plaza level continues.
Light weight soil installation to continues.
Installation of two 15,000 gallon rain water cisterns has begun.
Next week's (6/27/22 to 7/02/22) scheduled work activities:
G2
G2 Level is going 100% clean booties must be worn at all times.
Final touch up painting underway.
SAT (site acceptance testing) begins for bio-repository.
G1
7-T MRI calibration continues.
Ceiling grid installation in 3 T MRI suite continues.
Door installation continues.
Lighting fixtures in Mechanical rooms continues.
Continue installation of terrazzo flooring G-1 lobby.
Door installation continues.
Level 1
Café MEP rough in continues.
Operable Smoke panel installation continues.
Punch walk of L 1 South.
Atrium Terrazzo installation starts.
Level 2
Hanging drywall in East connector with HSRB – I.
Atrium "liquid light " installation to continue.
Level 3
Electrical trim out continues.
Symphony bench installation continues.
North Wing punch walk of L3 to begin.
Level 4
Fire alarm and electrical device trim out to continues.
Plumbing fixture installation continues.
Level 5
Light fixture installation.
Level 6
Installation of drywall ceiling in atrium to be completed.
Installation on balcony fascia continues.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Building Plenums and Louver Installation to continue.
Outside air duct Installation.
Installation of metal cooling tower platform and penthouse roof stairs.
Skin
Granite installation at South elevations continues.
Installation of marble at balconies continues.
installation Rosa Borba at SW Entry/elevation to continue.
HSRB – I Vivarium Expansion:
Ceiling tile installation to continue.
Site:
Rain water cistern excavation and installation to continue.
Side walk installation at East Plaza to continue.
LW soil installation to continue.
Comments