Construction Update - 5/13/22
- emoryhsrb2
- May 13, 2022
- 2 min read

This past week's (5/09/22 to /14/22) scheduled work activities:
G2
Installation of lab casework benches
Installation of Cyclotron continues
G1
Installation of ceiling grid in G – 1 Lobby continues.
trim out continues in BSL 3 areas.
Work in 7 T suite continues in preparation of delivery on 5/14/22
Work in 3 T suite continues.
Techniplast installation in aquatics suite continues.
Installation of case work continues various locations.
Level 1
9 wood ceiling installation continues.
Furniture installation has concluded part 1 of installation.
Installation of lab casework continues Lab table and benches.
Installation of 9 wood ceiling continues on L 1..
Drywall finishing at East Pedestrian bridge(s) Continues.
Removal of scaffolding in Atrium has finished.
Level 2
Plumbing fixture installation continues
Application of final coat of paint underway.
Installation of 9 wood ceilings continues.
Installation of furniture in write up areas and offices underway.
Level 3
Final coat of paint underway.
Monumental stair framing underway.
Carpet installation in North Offices has begun.
Installation of selected mill work has begun
Level 4
Fire alarm and lighting control wiring underway.
Fume hood tie ins continue.
Level 5
Atrium soffit Framing underway.
Interior atrium glass and handrailing continues.
Lab casework installation continues.
Level 6
Atrium Soffit framing continues.
Lab Case work was delivered, installation to begin.
ACT grid and hard ceiling installations underway.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Installation of East Trellis continues.
Delivery and installation of HVAC Louvers began on Thursday, 5/12/22.
Skin:
Marble installation continues on South & SW Façade of South Tower @ MC 11 & #12.
Installation of granite continues on the North elevation of building.
Installation of Rosa Borba at SW Entry continues.
Installation of glass on East Connector bridges continues.
HSRB – I Vivarium Expansion:
Stonhard floor installation is continues.
Installation of utility connections to HSRB – I continue.
Site:
Installation of trees on plaza level continues.
Installation of new curbs along Andrews Circle continues.
Next week's (5/16/22 to 5/21/22) scheduled work activities:
G2
Device trim out to continue.
G1
7-T suite build out to continue.
7-T MRI delivery and set up.
3-T MRI MEP rough in to continue.
BSL trim out to continue.
Level 1
9 wood ceiling installation continues.
Lab Tables and bench installation to continue.
Level 2
Atrium soffit Finishing.
Installation of 9 wood ceilings to continue.
Lab table installation.
Glass handrail installation to continue.
Level 3
Installation of Flooring in North Offices.
Final paint coat to be applied.
Level 4
Atrium soffit framing to continue.
Device trim out to continue.
Level 5
Sterilizer MEP connections underway.
Lab case work installation continues.
Ceiling tile installation.
Level 6:.
Prime paint South Labs.
Final Coat paint at doors and frames.
ACT device out continues.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
East Trellis installation to continue.
Louver Installation to continue.
AHU damper installation to begin.
Skin
Marble installation continues on MC 11, & 12 (master climber).
Granite installation at North elevation continues.
Installation of Rosa Borba to continue.
HSRB – I Vivarium Expansion:
ACT ceiling grid installation to begin..
Site:
Cellular concrete installation at plaza level to begin.
Side walk layout install at East Plaza to begin.