Construction Update - 4/30/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (4/19/21 to 4/24/21) scheduled work activities:

G2/G1

  • Drywall Framing for non-priority walls underway G-2.

  • Dispensing/Air Lock and Hot Cell walls G-2.

  • Overhead MEP installation continues G-2.

  • Installation of pre-action system at Cyclotron G-2.

  • Installation of recirculating pumps G-1.

  • Framing of walls continues G-1.

Level 1

  • Framing of non-priority walls- North Tower.

  • Installation of fire suppression system South Tower.

  • Detailing of stairs – North Tower.

  • Installation of window glazing South tower along Haygood.

Level 2

  • MEP installation & Sheet metal HVAC ductwork rough-in continues.

  • Framing of exterior windows – North Tower.

  • Steel bridge erection – Setting out riggers on L2 level East.

  • Installation of exterior CMU – North Tower.

Level 3

  • Overhead MEP Installation continues.

  • Framing of Exterior windows – North Tower.

  • Installing exterior CMU walls- North Tower – Area D.

  • Installation and detailing of stairs.

Level 4

  • Installing metal decking and studs on bridge.

  • Removal of wood shoring continues.

Level 5

  • Set west bridge steel and fabricate to fit.

  • Remove remaining wood shoring still in place.

Level 6

  • Wood shoring in place.

Mechanical Penthouse

  • Pouring of concrete pads in areas 1 & 2 were completed.

Site

  • Delivery of Micro-Grid equipment was completed 4/21 & 4/22.

  • Wiring of micro-grid engines continues.

Next week's (5/03/21 to 5/08/21) scheduled work activities:

G2 & G1

  • Starting installation of Catwalk G-1.

  • Drywall framing non-priority walls G-2.

  • Overhead MEP installation continues G2 & G1.

  • Installation of framing of headers for glass openings on G-2.

Level 1

  • Framing walls South tower.

  • Overhead MEP installation continues.

  • Installing fire suppression systems – Southeast end.

Level 2

  • Overhead MEP Installation continues.

  • Framing exterior windows - North tower.

  • Installing exterior CMU North tower Area.

Level 3

  • Top out priority walls.

  • Installation of Exterior CMU walls - North Tower.

  • Overhead MEP work continues.

Level 4

  • Frame and top out priority walls.

  • Begin Installation of CMU multiple areas.

Level 5

  • Begin installation of CMU walls multiple locations.

Level 6

  • Wood shoring is in place.

Mechanical Penthouse

  • Concrete pour area #3 scheduled for 5/3/21. Delayed due to concrete plant closure on Saturdays.

  • Finish installation of re-bar area #4 concrete pour, pour area #4 end of week weather permitting.

  • Delivery and setting of office air handling units on penthouse level.

Site

  • Installation of equipment continues.