The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.
This past week's (4/05/21 to 4/10/21) scheduled work activities:
G2/G1
Drywall Framing for non-priority walls underway G-2.
Installation of Elevator 3 & 4 shaft walls G-2.
Exterior masonry installation underway level G-2.
Overhead MEP installation continues on level G-1.
Lighting conduit installation continues G -1.
Electrical Room A build out continues level G-1.
Installation of waterproofing on top of G-1 plaza/exterior entry south tower.
Level 1
Overhead HVAC ductwork installation underway.
Installation of glazing and frames for exterior glass underway on L-1 North Tower.Installation of Anchoring and Horizontal frames for South Tower curtain wall L-1.
Level 2
Overhead conduit installation North Tower.
Framing and top out priority walls – North Tower.
Storm and Sanitary drains installed – North & South Tower.
Level 3
Shoring timbers removal level 3 pour 1 area.
Layout and Frame priority walls NE.
Detailing of Center Bridge steel.
Level 4
Shoring timbers in place.
Level 5
Shoring timbers in place.
Level 6
Concrete slab poured area 6-3.
Concrete slab poured # area 6-4.
Placing and setting columns – Level 6-4.
Mechanical Penthouse
Forming/placing of columns for in area 6-1.
Site
Pouring of planter wall footings.
Pouring of safety handrailing.
Installation of Micro-grid generator yard knee wall
Work on Exterior mock up continues.
View of North Tower while standing in Andrews Circle with back to Starvine bridge,
Next week's (4/12/21 to 4/17/21) scheduled work activities:
G2 & G1
Drywall framing Non-priority walls G- 2.
Installation of Elevator 3 & 4 shaft walls G-2 & G1.
Concrete equipment pads to be poured.
Level 1
Rough in of sheet metal ductwork.
Overhead MEP duct work continues.
Continue installation of anchoring and horizontal frames South Tower.
Level 2
Overhead conduit Installation North Tower.
Pour concrete at Center & West bridges.
Level 3
Shoring timbers removed at level 3 – 1 pour.
Continue with installation of steel Center Bridge.
Level 4
Steel detailing on center bridge work continues.
Level 5
Shoring timbers remains in place.
Level 6
Continue to place and set columns level 6 – pour 3.
Installation of columns for level 6 roof/floor of mechanical penthouse.
Mechanical Penthouse
Installation of formwork for areas at 6-1 continues.
Site
Pour Pads & Slab at Generator Yard/Micro-Grid.