top of page
Writer's pictureemoryhsrb2

Construction Update - 3/26/2021



The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (3/22/21 to 3/27/21) scheduled work activities:

G2/G1

  • Overhead MEP work continues.

  • Framing and hanging of walls.

  • Exterior wall shielding at Cyclotron installation Completed.

  • Continued building out electrical rooms on G1 & G2

  • Layout of walls continues with installation of top tracks.

  • Poured concrete ramp connecting loading dock areas of HSRB – I & II

  • Framing Priority walls at catwalk.

Level 1

  • Exterior Sheathing underway at SW corner of building.

  • Installation of anchoring & horizontal frames for Curtain wall.

  • Installation of conduit and piping underway at South Tower.

  • Priority wall installation underway North & South Towers continue.

  • Electrical Room C Build.

Level 2

  • Framing of Priority walls @ NE & NW areas of South Tower

  • Removal of shoring timbers in areas

  • West Bridge installation began.

Level 3

  • Shoring timbers remain in place.

  • West Bridge Installation and detailing of Center bridge underway.

Level 4

  • West Bridge Installation.

Level 5

  • Shoring timbers in place.

Level 6

  • Concrete formwork installation in areas 6-3 & 6-4.

  • Concrete poured area 6-2.

  • Rebar installation in area 6-3.

Mechanical Penthouse

  • Forming/placing of columns for in area 6-1.

Site

  • Andrews Circle grading work/road prep completed. Base coat of asphalt was installed on Sunday 3/21/21.

  • Pulling of electrical feeders in micro-grid vault continues.

  • Work on exterior mock up continues .

  • Work on Generator yard retaining wall continues.

Next week's (3/29/21 to 4/03/21) scheduled work activities:

G2 & G1

  • MEP overhead rough in continues.

  • Starting CMU walls at Loading Dock – G-1

  • Installation of fire caulking around MEP penetrations continue.

  • Frame, hang, and finish walls G1 & G2.

  • Electrical Room Build-Out continues G1 & G2.

Level 1

  • Overhead MEP rough-in South Tower.

  • Exterior Sheathing continues.

  • Priority Wall rough in on North Tower.

  • Installation of anchoring & Horizontal frames for curtain wall begins.

Level 2

  • Overhead MEP Installation North Tower.

  • Frame priority walls level 2 SW South Tower.

  • Detailing West Bridge.

  • Elevator steel and duct shaft steel installation has begun.

Level 3

  • Shoring timbers removed under level 4 -3 concrete pour.

  • Layout of Priority walls – NE.

Level 4

  • Steel detailing on center bridge work continues.

Level 5

  • Shoring timbers remains in place.

Level 6

  • Placement and setting of Columns Level 6-2, and 6-3.

  • Installation of form work for Level 6 concrete continues in area 4.

  • Concrete pour scheduled for area 6-3.

  • Installation of rebar in areas 6-3 & 6-4 to be completed.

Mechanical Penthouse

  • Installation of formwork for areas at 6-1 begins.

Site

  • Work at Micro-grid vault continues with pulling of electrical cables, and Ga Power work in GA Power transformer yard.

  • Installation of knee wall.


13 views0 comments

Recent Posts

See All

Comments


bottom of page