The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22 are the results of a DeKalb County Water line installation project.
This work is being managed by DeKalb County and not Emory's Planning, Design, and Construction Department.
We are told that weather permitting the project will take between 6 – 8 weeks and will be completed prior to Emory's Graduation weekend activities.
This past week's (3/21/22 to 3/26/22) scheduled work activities:
G2
Wood Door installation has begun.
GE has remobilized to continue installation of Cyclotron.
G1
Wood door installation has begun.
ACT ceiling framing is underway.
FRP door installation has continues in BSL areas.
Vivarium device trim out continues.
Framing, drywalling, and finishing of ceiling at Wonder Wall is underway
Level 1
Terrazzo installation has begun in North wing.
ACT tile installation in North and South wings has begun.
Fixture and device trim out continues.
Level 2
Plumbing fixture installation has begun.
Installation of CSP adaptors is underway.
Installation of glass at atrium window walls for computational lab areas continues.
Level 3
Installation of Atrium interior store front glass continues.
Installation of store front doors continues.
Tie in of the vent connects to Fume hoods has begun.
Level 4
ACT rough in and trim out is underway.
Installation of glass hand railings, in central atrium has begun.
Completed the Installation of air distribution grilles.
Level 5
Prime Paint continues in South Wing .
ACT framing has begun.
Level 6
Installation of trap primers has begun.
Work continues on the interior of the skylight.
ACM installation at exterior "eyebrow" is underway.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
Exterior Eyebrow metal panels is underway at MC 1 to 4.
Air Handling Units (AHU) device installation continues AHU 1.1, 1.2, & 1.4.
TPO & mod- bit roof installation continues.
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP continues.
Framing of walls in interior of space continues.
In wall MEP rough in continues.
Installation of utility connections to HSRB – I are underway.
Installation of Drywall continues in select areas.
Site:
Installation of trees on plaza level has begun.
Next week's (3/28/22 to 4/02/22) scheduled work activities:
G2
Installation of Biorepository to continues.
Wood Door installation continues.
GE to continue of the cyclotron installation.
G1
Installation of Stair #4 begins South East Corner of South wing.
FRP door installation in BSL areas continues.
Vivarium device trim out continues
Monumental stair installation continues. G1 to L1
Level 1
Fixture and Device trim out continues.
Installation of accessories in restrooms continues.
Level 2
Plumbing fixture installation continues.
ACT ceiling framing continues.
Installation of finishes for Wonder Wall ceiling continues.
Installation of interior glass store front doors and windows continues.
Level 3
Tie in Fume hoods scheduled be finished.
Level 4
Installation of glass handrails – center atrium continues.
Installation of air distribution grills scheduled to be completed.
ACT Rough in and trim out continues.
Level 5
Prime & Paint continues in South Wing.
Installation of ACT framing and hard ceilings in South Wing continues.
Level 6:.
ACM installation continues at the Eyebrow.
Hanging dry wall – South Wing.
ACM Installation at Eyebrow continues.
trap primer installation continues.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Skin
Marble installation continues on MC # 9, 10, & 11 (master climber).
Granite installation at West elevation continues.
Installation of Headers and Jambs at Structural curtain.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines and wall framing continues.
Rough – in of In-wall MEP continues.
Hang & Finish drywall.
Tie ins of utilities from HSRB – I expansion continues.
Site:
Selected finish grading in some areas.
Commentaires