Construction Update - 12/20/19
- emoryhsrb2
- Dec 20, 2019
- 1 min read
This past week's (12/16 – 12/21) scheduled work activities.
Storm Line A continues under Brumley Bridge.
Storm Detention Piping for Storm Detention Line B continues to be delivered to site.
Excavation for Storm detention piping at B line and removal of dirt continue.
All dump trucks used on site have blue flag with white number on them to help identify them on the roads if neighbors want to register a complaint.
Next week's (12/23 – 12/28 ) scheduled activities.
Excavation and installation of storm detention Line B continues.
Job Site closed 12/24 & 12/25.
Next weekly report will be issued on 1/3/20.