This past week’s (11/18 – 11/22) scheduled construction activities:
Installation of Storm A-line install continues.
Storm Detention System at A line install completed materials for Storm detention at B – line are being staged.
Line drilling continues along edge of HSRB – I.
Leveling of the site continues.
Next week’s look-ahead:
Storm A-line will be completed through A8.
Installation of new emergency egress pathway from café to loading dock area begins on Monday 11/25/19.
Site will be closed Thursday and Friday for Thanksgiving Holiday.
No construction update because of holiday on 11/29/19. Next update distributed on 12/6/19.