Construction Update - 11/22/2019

This past week’s (11/18 – 11/22) scheduled construction activities:


  • Installation of Storm A-line install continues.

  • Storm Detention System at A line install completed materials for Storm detention at B – line are being staged.

  • Line drilling continues along edge of HSRB – I.

  • Leveling of the site continues.

Next week’s look-ahead:


  • Storm A-line will be completed through A8.

  • Installation of new emergency egress pathway from café to loading dock area begins on Monday 11/25/19.

  • Site will be closed Thursday and Friday for Thanksgiving Holiday.

  • No construction update because of holiday on 11/29/19. Next update distributed on 12/6/19.