top of page
Writer's pictureemoryhsrb2

Construction Update - 11/06/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


This past week's (11/02/20 to 11/07/20) scheduled work activities:


G2

  • Electrical and Plumbing Overhead Rough-In .

  • Backfill Continues around G2.

G1

  • Poured final G -1 Level Foundation Wall.

  • Electrical and Plumbing Overhead Rough-In Continues.

Level 1

  • Installing Formwork for Pour 7 & 8.

  • Installing rebar in preparation of Pouring Level 1 Pour 6.

  • Waterproofing Level 1 Plaza for Backfill.

  • Installed re-bar in preparation of pouring level 1 pour 5 next week.

Vivarium Expansion

  • Poured Continuous Footing in Vivarium.

Next week's (11/09/20 to 11/14/20) scheduled work activities:

G2

  • Electrical and Plumbing Overhead Rough-In ongoing.

G1

  • Electrical and Plumbing Overhead Rough-In ongoing.

Level 1

  • Installing Formwork for Level 1 Pour 8 and 9.

  • Pouring Level 1 pour 5.

  • Waterproofing pour3 for backfill.

  • Installing rebar for pour 7.

Vivarium Expansion

  • Pouring Foundation Wall.



67 views0 comments

Recent Posts

See All

Comments


bottom of page