The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (10/19/20 to 10/24/20) scheduled work activities:
G2:
Continuing Backfilling G2 Foundation Walls
G1:
Continuing Foundation Wall Installation
Level 1:
Installing Formwork for Level 1 Pour 6.
Installation of rebar for Level 1 Pour 5.
Pouring level 1 pour 2.
MEP duct bank (utilidor) Installation
MEP rough in on level 1 pour 5.
Prepare Plaza Deck for backfill.
Level 1, pour 3 form work removed.
Level 1 pour 4 formwork removed.
Vivarium Expansion:
Continue Installing Vivarium Foundation System
Next week's (10/26/20 to 10/31/20) scheduled work activities:
G2:
Continuing backfilling G2 foundation walls.
G1:
Continue Foundation Wall Installation.
Level 1:
Installing formwork for Level 1, pour 7
Installing rebar for level 1, Pour 8.
Pouring Level 1, pour 5.
Pouring Level 1, pour 6.
MEP Rough in on Level 1 pour 6.
Backfill plaza deck.
Vivarium Expansion:
Continue Installing Vivarium Foundation System.
People like traveling in these buses so much and I also think that it a great experience because it feels just like a home. There are many websites which can tell us about it and the https://newcastlepergolas.com.au/ is one of those wonderful websites. I like to see many more pictures of these buses.