This past week's (1/27/20 to 2/1/20) scheduled work activities:
Deep excavation continues at the G2 Level of building.
Installation of new 24” concrete pipe to complete B line detention system along Andrews Circle and Loading Dock.
Demolition of Existing ADA ramp on HSRB – I.
Drilling and blasting of rock was conducted on 1/27, 1/29, and weather permitting will be done on 1/31.
Next week's (2/3/20 to 2/8/20) scheduled work activities:
Deep excavation for G-2 level to continue.
Drilling will continue for future rock removal on 2/3, 2/5, & 2/7.
Excavation work near existing HSRB – I loading dock will continue in preparation for the installation of new domestic & fire water lines in the next few weeks.
Comments