This past week's (1/21/22 to 1/29/22) scheduled work activities:
G2
Biorepository Installation continues.
Installation of wall devices continues.
G1
Stonhard floor Prep in BSL3 labs North & South continues.
Installation of plumbing fixtures is underway.
Drywall finishing in imaging center control rooms.
Installation of light fixtures in offices.
Wonder wall framing continues.
Level 1
Mullion Cap Installation.
Diffuser Installation continues.
HVAC rough in at East connector bridges.
Level 2
Laminated glass wall framing has begun.
Atrium soffit framing & electrical rough -in continues.
Level 3
Interior storefront glass installation has begun.
East monumental stair installation/welding completed to level 3.
Level 4
Hanging drywall North Tower.
Installation of wet lab lighting and service panels in South Tower.
Finishing and painting of drywall in wet lab areas is underway.
Level 5
Began Fire Alarm & lighting control wire rough-ins.
Level 6
Continued Installation of drains on eyebrows.
In wall MEP Rough-in continues.
Installation of “shoes” to support glass railings along edge of South tower atrium is all most completed.
Mechanical Penthouse
Eyebrow framing on Master Climbers #5 & MC#6 continues.
AHU device installation continues.
Installation of fire sprinkler piping continues at underside of skylight.
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP pipes continues.
Site:
Installation of light weight soils for plaza areas continues.
Next week's (1/31/22 to 2/05/22) scheduled work activities:
G2
Installation of Biorepository to continue.
Wall device Installation to continue.
G1
Installation of Stonhard in BSL 3 labs continue.
Plumbing fixture installation to continue.
Framing of feature walls continue.
Finishing drywall at imaging control rooms continues.
Installation of office light fixtures to continue.
Level 1
Mullion Cap installation to continue.
Diffuser installation to continue.
HVAC rough in at East Pedestrian bridges to continue.
Level 2
Framing of the laminated glass wall to begin.
Atrium soffit framing & electrical rough in to continue.
Level 3
Installation of next section of monumental stairs from LV3 to LV2.
Installation of interior storefront to continue.
Level 4
Lab Lighting and Service panel installation continues.
Hanging Drywall in – South Tower.
Level 5
Fire alarm & lighting control rough-in continues.
Level 6:
Continue Installation of eyebrow drains.
In wall MEP rough-ins continue.
Mechanical Penthouse
Skin
Marble installation continues on MC # 8, 9, & 10 (master climber).
Installation of TPO roofing continues on South Penthouse Roof continues.
Structural Curtin wall #1 glass installation pre begins.
Stucco installation at Skylight exterior continues (weather permitting).
Curtainwall 6 installation continues.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines continues.
Site:
Installation of light weight soils continues.
Excavation for North courtyard continues.