top of page
Writer's pictureemoryhsrb2

Construction Update - 1/28/2022


This past week's (1/21/22 to 1/29/22) scheduled work activities:

G2

  • Biorepository Installation continues.

  • Installation of wall devices continues.

G1

  • Stonhard floor Prep in BSL3 labs North & South continues.

  • Installation of plumbing fixtures is underway.

  • Drywall finishing in imaging center control rooms.

  • Installation of light fixtures in offices.

  • Wonder wall framing continues.

Level 1

  • Mullion Cap Installation.

  • Diffuser Installation continues.

  • HVAC rough in at East connector bridges.

Level 2

  • Laminated glass wall framing has begun.

  • Atrium soffit framing & electrical rough -in continues.

Level 3

  • Interior storefront glass installation has begun.

  • East monumental stair installation/welding completed to level 3.

Level 4

  • Hanging drywall North Tower.

  • Installation of wet lab lighting and service panels in South Tower.

  • Finishing and painting of drywall in wet lab areas is underway.

Level 5

  • Began Fire Alarm & lighting control wire rough-ins.

Level 6

  • Continued Installation of drains on eyebrows.

  • In wall MEP Rough-in continues.

  • Installation of “shoes” to support glass railings along edge of South tower atrium is all most completed.

Mechanical Penthouse

  • Eyebrow framing on Master Climbers #5 & MC#6 continues.

  • AHU device installation continues.

  • Installation of fire sprinkler piping continues at underside of skylight.

Skin:

  • Marble installation continues on MC #8, #9, & #10.

  • Installation of TPO roofing on South Penthouse roofs continues.

  • Structural curtainwall panting completed.

  • Stucco installation on exterior of Skylight has begun.

  • Curtain wall #6 installation has begun.

  • West Trellis Installation has begun.

HSRB – I Vivarium Expansion:

  • Installation of overhead MEP pipes continues.

Site:

  • Installation of light weight soils for plaza areas continues.

Next week's (1/31/22 to 2/05/22) scheduled work activities:

G2

  • Installation of Biorepository to continue.

  • Wall device Installation to continue.

G1

  • Installation of Stonhard in BSL 3 labs continue.

  • Plumbing fixture installation to continue.

  • Framing of feature walls continue.

  • Finishing drywall at imaging control rooms continues.

  • Installation of office light fixtures to continue.

Level 1

  • Mullion Cap installation to continue.

  • Diffuser installation to continue.

  • HVAC rough in at East Pedestrian bridges to continue.

Level 2

  • Framing of the laminated glass wall to begin.

  • Atrium soffit framing & electrical rough in to continue.

Level 3

  • Installation of next section of monumental stairs from LV3 to LV2.

  • Installation of interior storefront to continue.

Level 4

  • Lab Lighting and Service panel installation continues.

  • Hanging Drywall in – South Tower.

Level 5

  • Fire alarm & lighting control rough-in continues.

Level 6:

  • Continue Installation of eyebrow drains.

  • In wall MEP rough-ins continue.

Mechanical Penthouse

  • Eyebrow framing above Master Climbers #6 & #7 to continue.

  • AHU device installation continues.

Skin

  • Marble installation continues on MC # 8, 9, & 10 (master climber).

  • Installation of TPO roofing continues on South Penthouse Roof continues.

  • Structural Curtin wall #1 glass installation pre begins.

  • Stucco installation at Skylight exterior continues (weather permitting).

  • Curtainwall 6 installation continues.

HSRB – I Vivarium Expansion:

  • Installation of Overhead MEP lines continues.

Site:

  • Installation of light weight soils continues.

  • Excavation for North courtyard continues.


12 views0 comments

Recent Posts

See All

Comments


bottom of page