This past week's (1/17/22 to 1/22/22) scheduled work activities:
G2
Biorepository Installation has begun.
Installation of wall devices continues.
G1
Stonhard Prep in BSL# North & South Begins.
Aquatic tank support installation is complete.
Vivarium lighting installation continues.
Chiller plant start up is underway.
Vivarium door installation continues.
Wonder wall framing continues.
Ceiling grid installation continues.
Level 1
Terminate VAV’s and FCU’s.
Layout and framing of Granting Garden wall continues.
Interior Storefront glass installation continues.
Level 2
Prime & first coat of paint – North Tower
Atrium soffit framing continues.
Level 3
Prime & first coat of paint in South Tower.
East monumental stair installation continues.
Hanging drywall in North- Tower.
Level 4
Hanging drywall South Tower.
Installation of wet lab lighting and service panels in South Tower.
Installation of work stations in wet lab write up areas continues.
Level 5
Began the hanging of drywall. – South Tower.
Level 6
Continued Installation of drains on eyebrows.
Installation of fan coil units – North Tower.
installation of the Shoes (supports) for atrium hand railings is underway.
Mechanical Penthouse
Eyebrow framing on Master Climbers #5 & MC#6 continues.
Continue with electrical equipment connections and receptacle connections.
Skin
Marble installation on MC#7, 8 & 9.
Installation of TPO roofing on South Penthouse roofs continues.
HSRB – I Vivarium Expansion
fireproofing on underside of metal decking continues.
Installation of overhead MEP pipes continues.
Site
Installation of light weight soils for plaza areas continues after delay caused by wet weather.
Next week's (1/24/22 to 1/29/22) scheduled work activities:
G2
Installation of Biorepository to continue.
Wall device Installation to continue.
G1
Installation of Stonhard in BSL 3 labs continue.
Plumbing fixture installation begins.
Framing of feature walls continue.
Finishing drywall at imaging control rooms
Installation of office light fixtures.
Level 1
Mullion Cap installation.
Diffuser installation.
HVAC rough in at East Pedestrian bridges.
Level 2
Framing of the laminated glass wall to begin.
Atrium soffit framing & electrical rough in continues.
Level 3
Installation of next section of monumental stairs from LV3 to LV2.
Installation of interior storefront.
Level 4
Lab Lighting and Service panel installation continues.
Hanging Drywall in – North Tower.
Level 5
Fire alarm & lighting control rough-ins.
Level 6
Continue Installation of eyebrow drains.
In wall MEP rough-ins continue.
Mechanical Penthouse
Skin
Marble installation continues on MC # 8, 9, & 10 (master climber).
Installation of TPO roofing continues on South Penthouse Roof continues.
Curtin wall #1 installation of glass to begin in 2 weeks.
HSRB – I Vivarium Expansion
Installation of Overhead MEP lines continues.
Site
Installation of light weight soils continues.
Excavation for North courtyard continues.