Construction Update - 1/21/2022


This past week's (1/17/22 to 1/22/22) scheduled work activities:

G2

  • Biorepository Installation has begun.

  • Installation of wall devices continues.

G1

  • Stonhard Prep in BSL# North & South Begins.

  • Aquatic tank support installation is complete.

  • Vivarium lighting installation continues.

  • Chiller plant start up is underway.

  • Vivarium door installation continues.

  • Wonder wall framing continues.

  • Ceiling grid installation continues.

Level 1

  • Terminate VAV’s and FCU’s.

  • Layout and framing of Granting Garden wall continues.

  • Interior Storefront glass installation continues.

Level 2

  • Prime & first coat of paint – North Tower

  • Atrium soffit framing continues.

Level 3

  • Prime & first coat of paint in South Tower.

  • East monumental stair installation continues.

  • Hanging drywall in North- Tower.

Level 4

  • Hanging drywall South Tower.

  • Installation of wet lab lighting and service panels in South Tower.

  • Installation of work stations in wet lab write up areas continues.

Level 5

  • Began the hanging of drywall. – South Tower.

Level 6

  • Continued Installation of drains on eyebrows.

  • Installation of fan coil units – North Tower.

  • installation of the Shoes (supports) for atrium hand railings is underway.

Mechanical Penthouse

  • Eyebrow framing on Master Climbers #5 & MC#6 continues.

  • Continue with electrical equipment connections and receptacle connections.

Skin

  • Marble installation on MC#7, 8 & 9.

  • Installation of TPO roofing on South Penthouse roofs continues.

HSRB – I Vivarium Expansion

  • fireproofing on underside of metal decking continues.

  • Installation of overhead MEP pipes continues.

Site

  • Installation of light weight soils for plaza areas continues after delay caused by wet weather.

Next week's (1/24/22 to 1/29/22) scheduled work activities:

G2

  • Installation of Biorepository to continue.

  • Wall device Installation to continue.

G1

  • Installation of Stonhard in BSL 3 labs continue.

  • Plumbing fixture installation begins.

  • Framing of feature walls continue.

  • Finishing drywall at imaging control rooms

  • Installation of office light fixtures.

Level 1

  • Mullion Cap installation.

  • Diffuser installation.

  • HVAC rough in at East Pedestrian bridges.

Level 2

  • Framing of the laminated glass wall to begin.

  • Atrium soffit framing & electrical rough in continues.

Level 3

  • Installation of next section of monumental stairs from LV3 to LV2.

  • Installation of interior storefront.

Level 4

  • Lab Lighting and Service panel installation continues.

  • Hanging Drywall in – North Tower.

Level 5

  • Fire alarm & lighting control rough-ins.

Level 6

  • Continue Installation of eyebrow drains.

  • In wall MEP rough-ins continue.

Mechanical Penthouse

  • Eyebrow framing above Master Climbers #6 & #7.

  • AHU device installation continues.

Skin

  • Marble installation continues on MC # 8, 9, & 10 (master climber).

  • Installation of TPO roofing continues on South Penthouse Roof continues.

  • Curtin wall #1 installation of glass to begin in 2 weeks.

HSRB – I Vivarium Expansion

  • Installation of Overhead MEP lines continues.

Site

  • Installation of light weight soils continues.

  • Excavation for North courtyard continues.