This week’s (9/16 – 9/20) construction activities:
Site fence installation completed and installation of safety signage on exterior of fence progressing. -- Additional blue wind screens are being installed.
Delivery and installation of all 8 of JE Dunn office trailers completed. -- Plumbing installation completed, electrical and data installation underway.
Erosion/Sedimentation control fencing and other sediment control measures completed, and inspected by City of Atlanta.
Locations for web-cameras identified and approved by Emory & CHOA.
Furniture on Patio outside of HSRB – I has been relocated.
Next week’s (9/23 - 9/27) scheduled construction activities will include:
Grading Contractor will begin leveling of the site, assuming City of Atlanta issues LDP permit as expected..
Tree removal will begin.
JE Dunn Office Trailer installation will continue with installation of electrical, phone, and data hook ups. -- Office furniture and set up of work stations and conference rooms will begin.
Uncovering of abandoned chilled water pipes (from Turman West) along Andrews Cir. -- Abatement activities will begin 0n 10/1/19 once the pipes are carefully excavated.
Begin early stages of work for utility relocation near loading dock of HSRB - I