Construction Update - 4/18/2020
The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 24, 2020


Construction Update - 4/10/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 10, 2020


Construction Update - 4/3/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 6, 2020


Construction Update - 3/27/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 6, 2020
Construction Update - 3/22/2020
With COVID-1, the HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest...
emoryhsrb2
Mar 23, 2020


emoryhsrb2
Mar 23, 2020


Construction Update - 3/6/2020
This past week's (3/2/20 to 3/7/20) scheduled work activities: Blast #21 was held on Monday 3/2/20, No blast on Wednesday 3/4 due to...
emoryhsrb2
Mar 6, 2020


Construction Update - 2/28/2020
This past week's (2/24/20 to 2/29/20) scheduled work activities. Rock blasts # 18, #19, & #20 were successfully performed on Monday,...
emoryhsrb2
Feb 28, 2020


Construction Update - 2/21/2020
This past week's (2/17/20 to 2/22/20) scheduled work activities: Rock blasting was performed on Monday and Friday but cancelled on...
emoryhsrb2
Feb 21, 2020


Construction Update - 2/14/2020
This past week's (2/10/20 to 2/15/20) scheduled work activities: Rock blasts on Monday, Wednesday, and Friday numbers 13, 14, & 15....
emoryhsrb2
Feb 14, 2020


Construction Update - 2/7/2020
This past week's (2/3/20 to 2/8/20) scheduled work activities: Deep excavation continues at the G2 Level of building. Demolition of 60”...
emoryhsrb2
Feb 10, 2020


Construction Update - 1/31/2020
This past week's (1/27/20 to 2/1/20) scheduled work activities: Deep excavation continues at the G2 Level of building. Installation of...
emoryhsrb2
Jan 31, 2020


Construction Update - 1/17/20.
This past week's (1/13/20 to 1/17/20) scheduled work activities: Exploratory digging for the new loading dock entrance has begun....
emoryhsrb2
Jan 17, 2020


Construction Update - 1/3/20
This past week's (12/30/19 – 1/4/20) scheduled work activities. Storm Line A installation was completed. Excavation for Storm detention...
emoryhsrb2
Jan 3, 2020

Construction Update - 11/1/2019
This past week's (10/28 – 11/1/19) scheduled construction activities: Line drilling near HSRB – I will begin on Friday 11/1/19. -- This...
emoryhsrb2
Nov 5, 2019


Construction Update - 10/25/2019
This past week’s (10/21 – 10/26) scheduled construction activities will include: Completed control pond and swale Completed mobilization...
emoryhsrb2
Oct 25, 2019