Construction Update - 3/5/2021
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 7, 2021


Construction Update - 10/4/19
This week’s (9/30 – 10/4) construction activities: Grading Contractor (Dennis Taylor) will begin leveling of the site. Uncovering of...
emoryhsrb2
Oct 18, 2019


Construction Update - 9/27/19
This week’s (9/23 – 9/27) construction activities: ​ Erosion/Sedimentation control fencing and other sediment control measures completed,...
emoryhsrb2
Oct 18, 2019


Construction Update - 9/20/19
This week’s (9/16 – 9/20) construction activities: ​ Site fence installation completed and installation of safety signage on exterior of...
emoryhsrb2
Oct 18, 2019


Construction Update - 9/6/19
This week’s construction activities: Site fence installation began on 9/3/19. Delivery of JE Dunn office trailers began on 9/4/19. JE...
emoryhsrb2
Oct 18, 2019